We completly rebult balcony deck from 70’s The process took 10 days, it included: Buying Materials in Store. Removal all of Old Frame. Installation new Wooden Balcony Frame. Deck Installation on the Balcony. New Door Installation. Installation Door Trim. Door Screens Installation. Sealing the Door. Painting Exterior Doors.
We installed Siding wooden panels which we bought in Home Depot. The process took 2 days, it included: Buying materials in store.(1 psc sheet 6*4 around $30). Removal of old panels. Preparing walls (nail removal and material preparation)ю Marking and cutting material, lifting up. Siding plywood panels installation. Caulk on Exterior Siding Waterproof siding connection […]
We installed two wooden doors and the hardware. Processes included: 4,5 hours of work $600 labor. Picking up the solid core doors in Home Depot. Removed the old doors. Сustom trimming both doors from two sides. Routing doors for installing door hinges. Hanging doors. Door handles installation.